Waterford and Wexford Schools – Biomass Plantrooms

Delivering Prefabricated Biomass Plantrooms across Three School Sites
3 Schools

740kW of biomass heating

90%

Reduced reliance on gas-fired boilers

Location:

South East Ireland

Project Value:

€935,000k

Sector:

Education

Project Status:

Completed


Scope

Build and Installation of three prefabricated biomass boiler plantrooms and associated fuel storage installations.


Project Overview

Alternative Heat completed its scope of works on three biomass heating projects delivered under the Schools Energy Pathfinder Programme 2024 in County Wexford. The schemes at Enniscorthy Community College, Gorey Community School and St Peter’s College involved the installation of biomass boiler systems with a combined heating capacity of 740kW, supporting the transition to lower-carbon heating solutions across the education sector.

The projects included the delivery of three prefabricated biomass boiler plantrooms and associated fuel storage installations, providing a reliable and efficient renewable heating solution designed to meet the individual requirements of each school while supporting wider decarbonisation objectives.


Scope of Works

Key project elements included:

  • Design, Manufacture Offsite three prefabricated biomass boiler plantrooms
  • Integration of biomass boiler systems with capacities of 300kW, 230kW and 210kw.
  • Delivery, positioning and installation of plantroom modules on site
  • Testing and Commissioning
Each installation incorporated a 14-tonne fuel storage solution, designed to suit the specific operational requirements of the individual school and constructed using Alternative Heat’s framing system with external cladding.
Through a combination of offsite manufacture and carefully coordinated site activities during school holiday periods, the projects were delivered with minimal impact on school operations. The installations provide a reliable renewable heating solution tailored to the needs of each school while supporting the wider decarbonisation objectives of the programme.