Waterford and Wexford Schools – Biomass Plantrooms
Delivering Prefabricated Biomass Plantrooms across Three School Sites740kW of biomass heating
Reduced reliance on gas-fired boilers
Location:
South East Ireland
Project Value:
€935,000k
Sector:
Education
Project Status:
Completed
Scope
Build and Installation of three prefabricated biomass boiler plantrooms and associated fuel storage installations.
Project Overview
Alternative Heat completed its scope of works on three biomass heating projects delivered under the Schools Energy Pathfinder Programme 2024 in County Wexford. The schemes at Enniscorthy Community College, Gorey Community School and St Peter’s College involved the installation of biomass boiler systems with a combined heating capacity of 740kW, supporting the transition to lower-carbon heating solutions across the education sector.
The projects included the delivery of three prefabricated biomass boiler plantrooms and associated fuel storage installations, providing a reliable and efficient renewable heating solution designed to meet the individual requirements of each school while supporting wider decarbonisation objectives.
Scope of Works
Key project elements included:
- Design, Manufacture Offsite three prefabricated biomass boiler plantrooms
- Integration of biomass boiler systems with capacities of 300kW, 230kW and 210kw.
- Delivery, positioning and installation of plantroom modules on site
- Testing and Commissioning