85MW Data Centre, Paris

52No. Prefabricated Chiller & Water Treatment Plantrooms
95%

reduction in onsite labour

1

standardised plantroom type

Location:

Paris

Project Value:

£8,400,000 over 3 Phases

Sector:

Data Centre

Project Status:

Complete


Scope

52No. Prefabricated Chiller & Water Treatment Plantrooms


Project Overview

  • Design, procure, manufacture, FAT, logistics, site install and testing of 52No. Plantrooms.
  • OFCI chillers with a 40-50wk lead time
  • AH DfMA strategy meant lead time could be mitigated by preassembling all plantrooms in advance of the chiller delivery.
  • AH design team fully coordinated the plantrooms which enabled early manufacture.
  • Manufacture of the plantrooms inclusive of assembly, coatings, testing and QA checks in advance of chiller delivery.