85MW Data Centre, Paris
52No. Prefabricated Chiller & Water Treatment Plantrooms
95%
reduction in onsite labour
1
standardised plantroom type
Location:
Paris
Project Value:
£8,400,000 over 3 Phases
Sector:
Data Centre
Project Status:
Complete
Scope
52No. Prefabricated Chiller & Water Treatment Plantrooms
Project Overview
- Design, procure, manufacture, FAT, logistics, site install and testing of 52No. Plantrooms.
- OFCI chillers with a 40-50wk lead time
- AH DfMA strategy meant lead time could be mitigated by preassembling all plantrooms in advance of the chiller delivery.
- AH design team fully coordinated the plantrooms which enabled early manufacture.