10MW Data Centre, Dublin

Prefabricated CHW & Electrical Containment Fit-Out
95%

of Works Prefabricated and Modularised Offsite

8

Week Reduction in Programme

Location:

Dublin

Project Value:

£2,300,000

Sector:

Data Centre

Project Status:

Complete


Scope

Prefabricated CHW & Electrical Containment Fit-Out


Project Overview

Alternative Heat completed the offsite fabrication, delivery,                                  and onsite install of:

  • 4No. roof top chilled water lateral modules connecting the 4No. cooling towers to 4No. packaged pump rooms,
  • Internal chilled water riser modules
  • Internal chilled water lateral modules
  • Process water modules and electrical distribution modules for the DB6X datacentre.