Dalbeattie Learning Centre 500kW - Herz Biomass

500kW
Herz Biomass

Client: JBE Mechanical Services

Location: Dalbeattie, Scotland

Date of Installation: September 2016

Contract Value: £200k


System Overview


Dalbeattie High School is a small rural secondary school near the centre of Dalbeattie in the south of Scotland. The school has 380 pupils, with 40 staff.

Alternative Heat were employed to carry out the full design, supply, installation, testing and commissioning of a Bioomas Packaged Plantroom. The Packaged Plantroom consisted of 2No. 250kW Herz Firematic wood pellet boiler with associated auger system, integrated 42m³ wood pellet fuel store, MCC control panel and 2No. 6,000L buffer tanks wih insulation jackets.

Alternative Heat will undertake alls ervice and maintenance including future planned and responsive maintenance to the installed biomass system at this site. Full Revit 3D Plantroom layout drawings were provided to the client prior to commencement of fabrication works to ensure the best possible layout was achieved.