East Dunbartonshire Council 2.4MW - Herz Biomass

2.4MW
Herz Biomass

Client: East Dunbartonshire Council

Location: 6 EDC Sites

Date of Installation: Sep 2015

Contract Value: £1.2m


System Overview


Alternative Heat were appointed to design, manufacture, install and commission 6No. Biomass Heating Systems to replace the existing Gas and Oil heating systems.

Works involved a combination of retrofit works of existing plant rooms and the installations of Biomass Energy Centres:

  • Boclair Academy: 2No. 300kW Herz Firematic boilers instllaed into existing plant room
  • Castlehill Primary School: 250kW Herz Firematic boiler contained within a Biomass Energy Cabin
  • Clober Primary School: 250kW Herz Firematic boiler contained within a Biomass Energy Cabin
  • Gartconner Primary School: 250kW Herz Firematic boiler installed into existing plant room
  • Lenzie Academy: 800kW Herz BioFire boiler contained within a Biomass Energy Cabin
  • Oxgang Primary School: 250kW Herz Firematic boiler installed into existing plant room

Following the installation, we are contracted to provide the full operation, maintenace and fuel supply for the 6No. systems for a 6-year period.