NHS Ayrshire1.5MW - Packaged Plantroom

1.5MW
Packaged Plantroom

Client: NHS Ayrshire

Location: University Hospital, Ayr

Date of Installation: Feb 2018

Contract Value: £350k


System Overview


This project comprised of the design, co-ordination, supply, installation and commissioning of a new packaged plantroom facility for the provision of heat to NHS Ayrshire Hospital.

For this project we designed, supplied, installed, tested and commissioned a fully packaged plantroom complete with 1No. 1,500kW Herz BioFire boiler operating on wood pellet to supply base heat load of the site. The Herz BioFire 1,500kW boiler is a very high specification boiler, suitable for use with both wood chip and wood pellet. The boiler and central de-ashing system incorporated all the features necessary to minimise customer maintenance and maximise combustion efficiencies.

The Packaged Plantroom also consisted of an associated auger system (with the Herz Biomass Boiler), Herz central de-ashing system, BMS control and an 80,000L external buffer tank. Full REVIT 3D Plantroom Layout drawings were provideed to the client prior to commencement of fabrication works to ensure the best possible layout was achieved.