Belfast Health & Social Care Trust 364kW - Herz Biomass

2.6MW
Herz Biomass

Client: Belfast Health & Social Care

Location: Belfast

Date of Installation: Oct 2013

Contract Value: £300k


System Overview


Alternative Heat were employed to design, supply, install and commission 6No. Biomass Energy Cabins at various locations within the Belfast Health and Social Care Trust.

To ensure the existing services on each of the sites were not affected during connection we labelled, marked and prepped all the connections prior to any shutdown taking place, ensuring minimal disruption was achieved. Some of these works required out of hours and weekend shut downs to prevent downtime.

On contract completion we carried out a client demonstration and training to authorised personnel on the running and daily maintenance of the biomass boiler. We also provided the Health and Social Care Service with the maintenance procedures and Herz record keeping book.